Rakesh_Radhakrishnan


Project Start Date: Thu 2/6/03
Project Finish Date: Thu 6/5/03

Top Level Tasks

IDTask NameDurationStartFinish% CompleteCostWork
1Find Contractor23 daysThu 2/6/03Wed 3/5/030%$0.000 hrs
4Order & Deliver Furniture6 wksWed 3/5/03Tue 4/15/030%$0.000 hrs
5Hired Contractor0 daysWed 3/5/03Wed 3/5/030%$0.000 hrs
6Refurbish Building12 wksWed 3/5/03Mon 5/26/030%$0.000 hrs
7Order & Deliver Equipment4 wksTue 4/15/03Tue 5/13/030%$0.000 hrs
8Order & Deliver New Products2 wksTue 5/13/03Mon 5/26/030%$0.000 hrs
9Hire & Train Local staff6 wksTue 4/22/03Mon 6/2/030%$0.000 hrs
10Construction complete0 daysMon 5/26/03Mon 5/26/030%$0.000 hrs
11Set-up Furniture, Equipment1 wkTue 5/27/03Mon 6/2/030%$0.000 hrs
12Clean Up2 daysMon 6/2/03Wed 6/4/030%$0.000 hrs
13Stock Display1 dayWed 6/4/03Thu 6/5/030%$0.000 hrs
14Grand Opening0 daysThu 6/5/03Thu 6/5/030%$0.000 hrs